Friday, September 15, 2017

[Mahagunpuram] REQUEST TO KINDLY RE-START THE WORK RELATING TO INSTALLATION OF ALREADY APPROVED ONE MORE LIFT (THIRD LIFT) WITH ANTI RESCUE DEVICE [ARD] AT ALL THE BLOCKS (TOWERS) OF MAHAGUNPURAM, NH-24, MEHRAULI, GHAZIABAD – 201002, UTTAR PRADESH. [2 Attachments]

[Attachment(s) from anasee2162@yahoo.in [MahagunpuramRWA] included below]

REQUEST TO KINDLY RE-START THE WORK RELATING TO INSTALLATION OF ALREADY APPROVED ONE MORE LIFT (THIRD LIFT) WITH ANTI RESCUE DEVICE [ARD] AT ALL THE BLOCKS (TOWERS) OF MAHAGUNPURAM, NH-24, MEHRAULI, GHAZIABAD – 201002, UTTAR PRADESH.

 

All residents residing at Mahagunpuram; MP-AOA (Regd) and AOAFG (Regd) are also requested to send their requests on the above subject in the following way as it will help in speedy implementation of the same :-


---------- Forwarded message ----------

From :  Anand Kumar Sharma <anasee2162@gmail.com>

Date :  Sat, Sep 16, 2017 at 12:12 AM

Subject :  REQUEST TO KINDLY RE-START THE WORK RELATING TO INSTALLATION OF ALREADY APPROVED ONE MORE LIFT (THIRD LIFT) WITH ANTI RESCUE DEVICE [ARD] AT ALL THE BLOCKS (TOWERS) OF MAHAGUNPURAM, NH-24, MEHRAULI, GHAZIABAD – 201002, UTTAR PRADESH.

 

To :  Mahagun Customer Care <customercare@mahagunindia.com>, "info@mahagunindia.com" <info@mahagunindia.com>, Mahagun India <info.mahagunindia@gmail.com>, marketing@mahagunindia.com, Dhiraj Jain <mahagun@gmail.com>, scsharma@mahagunindia.com, Mayank Aggarwal <mayank.fbd@gmail.com>, anil jain <aniljain.mahagun@gmail.com>, Ajeet Chaubey <ajeetchaubey.csk@gmail.com>, Mahagun Puram <mahagunpuram.csk@gmail.com>, santosh Helpline <helplinegda@gmail.com>, vcgda ghaziabad <gdagzb@gmail.com>

Cc :  "Gen V. K. Singh" <eloksabhagzb@gmail.com>, mosvks@mea.gov.in, MOS VKS <mosvkso@mea.gov.in>, vksingh.mp@sansad.nic.in, cmup@nic.in, Yogi Adityanath <yogiadityanath72@gmail.com>, upinformation@nic.in, ncrpb-ms@nic.in, ncrpb-dr@nic.in, ncrpb-jd1@nic.in, ncrpb-aa02@nic.in, csup@up.nic.in, shreeprakash54@hotmail.com, awas@up.nic.in, "Awas Bandhu U.P." <awasbandhu@gmail.com>, SO NAGAR VIKAS <so.nagarvikas@gmail.com>, diruplb@nic.in, ISHWAR CHAND JINDAL <icjindal@gmail.com>, Gaurav Dwivedi <ergauravdwivedi@gmail.com>, ashvanityagi168@gmail.com, Ashvani Tyagi <tyagia.007@gmail.com>, Saurabh Bansal <tosaurabh7@yahoo.co.in>, gargparveen1971@yahoo.co.in, RWA uttam g <uttam.singh@kanbaninfosystem.com>, Jatinder kumar <jks.gzb@gmail.com>, cyberarvind@yahoo.com, Arvind Tiwari <er.arvindtiwari@gmail.com>, "saxena111@gmail.com" <saxena111@gmail.com>, ajaykaushik74@yahoo.com, mahagunpuram aoa <mahagunpuramaoa@gmail.com>, "sheetal_tyg@yahoo.co.in" <sheetal_tyg@yahoo.co.in>, Sheetal Tyagi <sheetaltyagi1981@gmail.com>, surjeet singh <surjeet_cavs@yahoo.co.uk>, TAPAN KUMAR <smarttapan@yahoo.com>, TAPAN panigrahi <smartone.tapan@gmail.com>, gauravvanshi@yahoo.com, tanweer1008@yahoo.com, Avdhesh Kumar <avdheshks@gmail.com>, vnrsa@yahoo.com, Subhash Verma <subhashchandraverma@gmail.com>, AOA Federation Ghaziabad <aoafedgzb2015@gmail.com>, RWA Federation Gzb <rwafedgzb6@gmail.com>, Tejandra Pal Tyagi <tptyagi@gmail.com>, Abid Hussain Barlaskar <abidhussainbarlaskar@gmail.com>

To

 

Vice President (Facility Management) / Director,

Mahagun Group, Mahagun India Private Limited

(Mahagun Real Estate Private Limited),

Corporate Office : Office No. 44, Tower – B,

4th Floor, Corenthum, Sector – 62,

NOIDA – 201309, Uttar Pradesh.

 

Vice Chairman,

Ghaziabad Development Authority (GDA),

Vikas Path, Near Old Bus Stand,

Ghaziabad – 201001,

Uttar Pradesh.

 

SUBJECT :  REQUEST TO KINDLY RE-START THE WORK RELATING TO INSTALLATION OF ALREADY APPROVED ONE MORE LIFT (THIRD LIFT) WITH ANTI RESCUE DEVICE [ARD] AT ALL THE BLOCKS (TOWERS) OF MAHAGUNPURAM, NH-24, MEHRAULI, GHAZIABAD – 201002, UTTAR PRADESH.

 

Respected Sir,

 

1.      Kindly refer to my requests dated 25th April, 2015; 9th May, 2015; 15th June, 2015; 4th July, 2015; 5th August, 2015; Speed Post Letter dated 20th September, 2015; 5th December, 2015; 19th March, 2016; 25th May, 2016; 1st July, 2016; 12th August, 2016 2nd September, 2016; Thanks letter dated 14th September, 2016; 29th October, 2016; Thanks letter dated 22nd November, 2016; Thanks letter dated 26th January, 2017; 8th June, 2017; 5th July, 2017; 17th July, 2017; 2nd August, 2017 and 19th August, 2017 on the above subject.  I am, once again, requesting you to kindly re-start the work relating to installation of already approved one more Lift (Third Lift) with ARD at all the Blocks (Towers) of Mahagunpuram, NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh.

 

2.      Residents had booked Flats in various Blocks (Towers) of Project 'Mahagunpuram' at NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh with effect from May, 2009 onwards.  Registry from the Registration Office, Tehsil, Ghaziabad and Physical Possession from Builder of the Flats in various Blocks (Towers) by the residents of Mahagunpuram, NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh had been done with effect from November, 2012 onwards.  Also, our MP-AOA [Mahagunpuram Apartment Owners Association], Mahagunpuram, NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh] had been registered with the Competent Authority in December, 2013.

 

3.      At present, there are only two lifts provided / installed for all the Blocks (Towers) of Mahagunpuram, NH-24, Mehrauli, Ghaziabad, Uttar Pradesh for the residents of Mahagunpuram, NH-24.  The residents are facing great difficulties regarding this.  The ratio of lifts with regard to the number of floors for all the Blocks (Towers) of Mahagunpuram, NH-24 is very low due to which too much hardship is being faced by the residents of Mahagunpuram, NH-24.  At least, one more lift (third lift) may please be provided / installed for all the Blocks (Towers) of Mahagunpuram, NH-24 for the residents so that the residents could not face difficulties in future as they are facing presently.  There is already provision for that and also the fact that there is enough space for two more lifts adjacent to the present two lifts in all the Blocks (Towers) of Mahagunpuram, NH-24 so that at least one more lift (third lift) can be provided / installed immediately for the benefits of residents of Mahagunpuram, NH-24 for which we all will be highly grateful to you all.

 

4.      Kindly refer to reply dated 2nd August, 2016 received by me from the Office of Hon'ble Chief Minister of Uttar Pradesh (apkacm-up@nic.in) regarding providing/installing one more Lift (Third Lift) for all Blocks (Towers) of Mahagunpuram, NH-24, Ghaziabad, as under:-

 

"Your e-mail dated 19th March, 2016 on the above subject has been received by the Office of Hon'ble Chief Minister and the same has been forwarded to Chief Secretary / Secretary – Housing and Urban Planning / Chairman – Ghaziabad Development Authority, Government of Uttar Pradesh, Lucknow (Uttar Pradesh) for further necessary action".

 

5.      Also, kindly refer to reply dated 9th September, 2016 received by me from the Office of Hon'ble Chief Minister of Uttar Pradesh (apkacm-up@nic.in) regarding providing/installing one more Lift (Third Lift) for all Blocks (Towers) of Mahagunpuram, NH-24, Ghaziabad, as under:-

 

"Your e-mail dated 12th August, 2016 on the above subject has been received by the Office of Hon'ble Chief Minister of Uttar Pradesh and the same has been forwarded to Chief Secretary / Secretary – Housing and Urban Planning / Chairman – Ghaziabad Development Authority, Government of Uttar Pradesh, Lucknow (Uttar Pradesh) for further necessary action".

 

6.      In view of the above and also the fact that the ratio of lifts with regard to the number of floors for all the Blocks (Towers) of Mahagunpuram, NH-24 is very low, we requested that necessary instructions may please be issued to the concerned officers / officials to provide one more lift (third lift) for all the Blocks (Towers) of Mahagunpuram, NH-24, Mehrauli, Ghaziabad at the earliest so that the residents of Mahagunpuram, NH-24, Ghaziabad could not face difficulties in future as they are facing presently. 

 

7.      Many thanks for confirming on 14th September, 2016 the approval of one more Lift (Third Lift) with Anti Rescue Device [ARD] for all the Blocks (Towers) of Mahagunpuram, NH-24, Mehrauli, Ghaziabad.

 

8.      Also, many thanks for placing the order for the installation of one more lift (Third Lift) with ARD for the Blocks (Towers) of Mahagunpuram, NH-24, Mehrauli, Ghaziabad.  Kindly refer to letter No. MREPL/CONT/LOI/OTIS/16-17/7078 dated 20th December, 2016 (copy attached) of Mahagun (Mahagun Real Estate Private Limited), Sector – 62, NOIDA - 201301 to OTIS Elevator Company (India) Limited, Malad (West), Mumbai - 400064 regarding 'Letter of Intent for installation of one more lift (Third Lift) for Blocks (Towers) of Mahagunpuram Phase – I, NH-24, Mehrauli, Ghaziabad (Uttar Pradesh)'.  We all are highly grateful to you for that.

 

9.      Kindly refer to the following Notice of MP-AOA of April, 2017 regarding starting of work relating to installation of Third Lift with Anti Rescue Device [ARD] for the Blocks (Towers) of Mahagunpuram, NH-24, Mehrauli, Ghaziabad, as under :-

 

"नमस्कारसभी साथियों को हर्ष के साथ सूचित किया जाता हैहमारी सोसाइटी मे तृतीय लिफ्ट से सम्बंधित सिविल का कार्य प्रारम्भ हो चुका है।अभी इसको रिद्धी और गंगा टॉवर से आरम्भ किया गया है।  जल्द ही यह सिविल सम्बंधित कार्य सभी टॉवर मे पूर्ण किया जाएगाजिसका सम्भावित समय 2 माह का है। इसके तत्पश्चात ही ओटिस के द्वारा लिफ्ट लगाने 'Installation' का कार्य आरम्भ हो जायेगा।  साथ हीसभी से विनती है इस कार्य के चलते धूल ,टूटफूट आदि समस्याओ की दिक्कत  सकती है। जिसके लिये हमें खेद है। इसके अतिरिक्त कॉरिडोर मे बच्चो के आवागमन के समय सुरक्षा का भी पूर्ण ध्यान रखने मे सहयोग प्रदान करे।  हमारी कोशिश होगीइस निर्माण को हर सम्भावित सुरक्षा के दायरे मे करवाया जाये।  इस विकास कार्य की आप सभी मित्रों को ढेरी बधाइयाँ।  धन्यवाद।  आपकी एम पी –   "

 

10.    In addition to above, kindly also refer to Notice of Team CSK of April, 2017 (copy attached) regarding starting of work relating to installation of Third Lift with Anti Rescue Device [ARD] for the Blocks (Towers) of Mahagunpuram, NH-24, Mehrauli, Ghaziabad.

 

11.    After the issue of above Letter of Intent dated 20th December, 2016 by Mahagun and two Notices of April, 2017 by MP-AOA / Team CSK, it was hoped that the Third Lift with ARD will be installed for the Blocks (Towers) of Mahagunpuram soon.

 

12.    Till date, the work relating to installation of Third Lift with Anti Rescue Device [ARD] for all the Blocks (Towers) of Mahagunpuram, NH-24, Mehrauli, Ghaziabad has not been started even after the approval of it in September, 2016.

 

13.    In view of the above, it is, once again, requested that necessary instructions may please be issued to the concerned officers / officials to re-start the work relating to installation of already approved Third Lift with Anti Rescue Device (ARD) for all the Blocks (Towers) of Mahagunpuram, NH-24, Mehrauli, Ghaziabad at the earliest so that the residents of Mahagunpuram, NH-24, Ghaziabad could not face difficulties in future as they are facing presently. 

 

14.    Kindly acknowledge and confirm.

 

Regards.

 

Anand Kumar Sharma

Date :  16th September, 2017.

Address : Flat No. 1106, Riddhi Block (Tower), Mahagunpuram, NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh.

 

Encls : As stated above.

 

Copy for information and further necessary action please to :-

 

1.      Hon'ble Minister of State for External Affairs / Overseas Indian Affairs and Hon'ble Member of Parliament (Lok Sabha : Ghaziabad Constituency), 2/27, Raj Nagar, Ghaziabad – 201002, Uttar Pradesh.  Kindly acknowledge and confirm.

 

2.      Hon'ble Chief Minister of Uttar Pradesh, Lucknow – 226001, Uttar Pradesh.  Kindly acknowledge and confirm.

 

3.      Member Secretary, National Capital Region Planning Board (Ministry of Urban Development), Core–IV B, First Floor, India Habitat Centre, Lodhi Road, New Delhi – 110003.  Kindly acknowledge and confirm.

 

4.      Chief Secretary / Secretary – Housing & Urban Planning / Chairman – Ghaziabad Development Authority, Government of Uttar Pradesh, Lucknow – 226001, Uttar Pradesh.  Kindly acknowledge and confirm.

 

5.      President / General Secretary / Executive Members of Mahagunpuram Apartment Owners Association (MP-AOA) [Regd] of Mahagunpuram, NH-24, Mehrauli, Ghaziabad, Uttar Pradesh – 201002.  You are also requested to kindly write on the similar lines as it will help in speedy implementation of the same.  Kindly acknowledge and confirm.

 

6.      President, Apartment Owners Associations Federation Ghaziabad (AOAFG) [Regd], Registered Head Office : 133 – B, Model Town East, Ghaziabad – 201009, Uttar Pradesh.  You are also requested to kindly write on the similar lines as it will help in speedy implementation of the same.  Kindly acknowledge and confirm.

 




__._,_.___

Attachment(s) from anasee2162@yahoo.in [MahagunpuramRWA] | View attachments on the web

2 of 2 Photo(s)


__,_._,___

Sunday, September 10, 2017

[Mahagunpuram] NH-24 Widening work started between the stretch 'UP Gate' and 'Dasna' (via Mahagunpuram) of 14-Lane Delhi - Meerut Expressway. [1 Attachment]

[Attachment(s) from ANAND KUMAR SHARMA included below]

NH-24 Widening work started between the stretch 'UP Gate' and 'Dasna' (via Mahagunpuram) of 14-Lane Delhi - Meerut Expressway.


__._,_.___

Attachment(s) from ANAND KUMAR SHARMA | View attachments on the web

1 of 1 Photo(s)


Posted by: ANAND KUMAR SHARMA <anasee2162@yahoo.in>


-------------AAAAAAAAAAA-----------------------





__,_._,___

[Mahagunpuram] NH-24 Widening work started between the stretch 'UP Gate' and 'Dasna' (via Mahagunpuram) of 14-Lane Delhi - Meerut Expressway. [1 Attachment]

[Attachment(s) from ANAND KUMAR SHARMA included below]

NH-24 Widening work started between the stretch 'UP Gate' and 'Dasna' (via Mahagunpuram) of 14-Lane Delhi - Meerut Expressway.

On 28-Jul-2017 8:19 PM, ANAND KUMAR SHARMA <anasee2162@yahoo.in> wrote:
Widening of NH-24 : Work between UP Gate and Dasna to start from 01 August 2017.

On 14-Aug-2016 5:13 PM, "anasee2162@yahoo.in [MahagunpuramRWA]" <MahagunpuramRWA@yahoogroups.com> wrote:
[Attachment(s) from anasee2162@yahoo.in [MahagunpuramRWA] included below]

Request to start the work after Foundation Laying Stone by Hon'ble Prime Minister of India on 31st December, 2015 of 14 – Lane Delhi – Meerut Expressway Project [Widening of NH–24 from UP Gate (Delhi – UP Border) to Dasna and from UP Gate (Delhi – UP Border) to Meerut via Dasna] on Hybrid Annuity Model.

 

All residents residing along NH-24, Ghaziabad; Mahagunpuram, NH-24, Mehrauli, Ghaziabad; MP-AOA (Mahagunpuram Apartment Owners Association); AOA Federation Ghaziabad (Regd); AOAs/RWAs of Housing Projects along NH-24, Ghaziabad are also requested to send their requests on the above subject in the following way as it will help in speedy implementation/completion of the same :-

 

---------- Forwarded message ----------

From :  Anand Kumar Sharma <anasee2162@gmail.com>

Date :  Sun, Aug 14, 2016 at 5:01 PM

Subject :  Request to start the work after Foundation Laying Stone by Hon'ble Prime Minister of India on 31st December, 2015 of 14 – Lane Delhi – Meerut Expressway Project [Widening of NH–24 from UP Gate (Delhi – UP Border) to Dasna and from UP Gate (Delhi – UP Border) to Meerut via Dasna] on Hybrid Annuity Model.

 

To :  nitin.gadkari@nic.in, secy-road@nic.in, Sanjay Mitra <secyrth@gmail.com>, vaibhav.dange@nic.in, rajgopal.sharma@nic.in, wadekar11@yahoo.co.in, sandeepkumar.rth@nic.in, rohit.kumar@nic.in, rajkumar.arora@nic.in, pradeep.rawal@nic.in, chairman@nhai.org, memberppp@nhai.org, memberfinance@nhai.org, memberadmin@nhai.org, Atul Kumar <atulkumar@nhai.org>, akmarwaha@nhai.org, mkjain@nhai.org, anandksingh@nhai.org, prasadranjeeta@nhai.org, pawars@nhai.org, rajeevyadav@nhai.org, c.ekambaram@nic.in, TT Negi <negitt4@gmail.com>, jkgoyal@nhai.org, kumarshashank@nhai.org

Cc :  "Gen V. K. Singh" <eloksabhagzb@gmail.com>, MOS VKS <mosvkso@mea.gov.in>, vksingh.mp@sansad.nic.in, ncrpb-ms@nic.in, ncrpb-crp@nic.in, ncrpb-dr@nic.in, ncrpb-jd1@nic.in, ncrpb-aa02@nic.in, ncrcellup@gmail.com, ISHWAR CHAND JINDAL <icjindal@gmail.com>, Gaurav Dwivedi <ergauravdwivedi@gmail.com>, Saurabh Bansal <tosaurabh7@yahoo.co.in>, gargparveen1971@yahoo.co.in, RWA uttam g <uttam.singh@kanbaninfosystem.com>, Jatinder kumar <jks.gzb@gmail.com>, cyberarvind@yahoo.com, Arvind Tiwari <arvind.amity29@gmail.com>, Arvind Tiwari <er.arvindtiwari@gmail.com>, "saxena111@gmail.com" <saxena111@gmail.com>, ajaykaushik74@yahoo.com, SHEETAL TYAGI <sheetal_tyg@yahoo.co.in>, Sheetal Tyagi <sheetaltyagi1981@gmail.com>, surjeet singh <surjeet_cavs@yahoo.co.uk>, mahagunpuram aoa <mahagunpuramaoa@gmail.com>, TAPAN KUMAR <smarttapan@yahoo.com>, TAPAN panigrahi <smartone.tapan@gmail.com>, gauravvanshi@yahoo.com, tanweer1008@yahoo.com, Avdhesh Kumar <avdheshks@gmail.com>, vnrsa@yahoo.com, AOA Federation Ghaziabad <aoafedgzb2015@gmail.com>, Tejandra Pal Tyagi <tptyagi@gmail.com>, RWA Federation Gzb <rwafedgzb6@gmail.com>, vishal <vishal@hamaraghaziabad.com>

To

 

Hon'ble Minister for Road Transport and Highways,

Ministry of Road Transport and Highways (MoRT&H)

Transport Bhawan,

1, Parliament Street,

New Delhi – 110001.

 

Chairman,

National Highways Authority of India,

G 5 & 6, Sector – 10, Dwarka,

New Delhi – 110075

 

Subject :  Request to start the work after Foundation Laying Stone by Hon'ble Prime Minister of India on 31st December, 2015 of 14 – Lane Delhi – Meerut Expressway Project [Widening of NH–24 from UP Gate (Delhi – UP Border) to Dasna and from UP Gate (Delhi – UP Border) to Meerut via Dasna] on Hybrid Annuity Model.

 

Respected Sir,

 

1.      Kindly refer to my requests dated 6th January, 2013; 9th January, 2013; 7th May, 2013, 8th May, 2013; 28th May, 2013; 17th August, 2014; 23rdAugust, 2014; 8th November, 2014; 6th December, 2014; 26th December, 2014; 28th April, 2015; 24th June, 2015; 13th October, 2015; 26th October, 2015; 21st November, 2015 and 7th May, 2016 on the above subject.  The above subject matter is pending since long.  I am, once again, requesting for the same.

 

2.      Kindly refer to replies dated 29th May, 2013; 30th May, 2013 and 28th August, 2014 received from Ministry of Road Transport and Highways (MoRT&H) / National Highways Authority of India (NHAI) on the above subject.

 

3.      Kindly refer to Requests for Proposal (Letters of Invitation) dated 4th March, 2014; 27th July, 2015; 8thSeptember, 2015; 9th October, 2015; 23rd October, 2015; 9th November, 2015; 27th November, 2015 and 6th May, 2016 of National Highways Authority of India (Ministry of Road Transport and Highways), New Delhi on the above subject.

 

4.      Hon'ble Prime Minister of India had laid the foundation stone of 14 – Lane Delhi – Meerut Expressway Project [Widening of NH–24 from UP Gate (Delhi – UP Border) to Dasna and from UP Gate (Delhi – UP Border) to Meerut via Dasna] on 31st December, 2015 from Plot No. A – 33, Sector – 62, NOIDA, Uttar Pradesh (copies of photos attached of the function).  The special invitees for this function (foundation laying stone of 14 – Lane Delhi – Meerut Expressway Project by Hon'ble Prime Minister of India on 31st December, 2015) were Hon'ble Minister for Road Transport and Highways; Hon'ble Minister of State (Independent Charge) for Culture, Tourism & Civil Aviation & Hon'ble Member of Parliament (Lok Sabha : Gautam Buddha Nagar Constituency); Hon'ble Minister of State for Road Transport and Highways; Hon'ble Minister of State for External Affairs / Overseas Indian Affairs & Hon'ble Member of Parliament (Lok Sabha : Ghaziabad Constituency) and other important VIPs.  

 

5.      It seems that, even after the Hon'ble Prime Minister of India had laid the foundation laying stone on 31st December, 2015 of 14 – Lane Delhi – Meerut Expressway Project from Delhi to Meerut (via UP Gate, NH-24, Ghaziabad / Mahagunpuram, NH-24 / Dasna), the work relating to it has yet to be started.

 

6.      In view of the above, please confirm that the work relating to 14 – Lane Delhi – Meerut Expressway Project [widening of NH-24 from UP Gate (Delhi-UP Border) to Dasna and from UP Gate (Delhi-UP Border) to Meerut via Dasna] has been started or not.  If it has not yet been started, then kindly intimate when the work relating to this will start and complete as already considerable delay has happened in this regard.  We all will be highly grateful to you for that.

 

7.      Kindly acknowledge and confirm.

 

Regards,

 

Anand Kumar Sharma

Date : 14th August, 2016.

Address : Flat No. 1106, 11th Floor, Riddhi Block, Mahagunpuram, NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh.

 

Attachments : As stated above.

 

Copy for information and further necessary action to :-

 

1.      Hon'ble Minister of State for External Affairs / Overseas Indian Affairs and Hon'ble Member of Parliament (Lok Sabha : Ghaziabad Constituency), 2/27, Raj Nagar, Ghaziabad - 201002, Uttar Pradesh.  Kindly acknowledge and confirm.

 

2.      Member Secretary, National Capital Region Planning Board (Ministry of Urban Development), Core–IV B, First Floor, India Habitat Centre, Lodhi Road, New Delhi – 110003].  Kindly acknowledge and confirm.

 

3.      Commissioner, NCR  Planning & Monitoring Cell (UP), Town & Country Planning Department, Navyug Market, Second Floor, Nagar Nigam Bhawan (Commercial Building), Ghaziabad, Uttar Pradesh – 201001.  Kindly acknowledge and confirm.

 

4.      President / General Secretary / Executive Members of Mahagunpuram Apartment Owners Association (MP-AOA) [Regd.] of Mahagunpuram, NH-24, Mehrauli, Ghaziabad, Uttar Pradesh – 201002.  Kindly acknowledge and confirm.

 

5.      President, Apartment Owners Associations Federation Ghaziabad (AOAFG) [Regd] : 133 – B, Model Town East, Ghaziabad – 201009, Uttar Pradesh.  Kindly acknowledge and confirm.

 

6.      Editor, Hamara Ghaziabad, 304, Ansal's Shivam Tower, Raj Nagar District Centre, Ghaziabad – 201001, Uttar Pradesh.  Kindly acknowledge and confirm.

 








__._,_.___

Attachment(s) from ANAND KUMAR SHARMA | View attachments on the web

1 of 1 Photo(s)


Posted by: ANAND KUMAR SHARMA <anasee2162@yahoo.in>


-------------AAAAAAAAAAA-----------------------





__,_._,___

Wednesday, September 6, 2017

[Mahagunpuram] REQUEST FOR PROVIDING SEWER CONNECTION FOR MAHAGUNPURAM, NH-24, MEHRAULI, GHAZIABAD – 201002, UTTAR PRADESH FROM BUILDER (MAHAGUN GROUP) / GHAZIABAD MUNICIPAL CORPORATION (NAGAR NIGAM GHAZIABAD) / GHAZIABAD DEVELOPMENT AUTHORITY (GDA). [10 Attachments]

[Attachment(s) from anasee2162@yahoo.in [MahagunpuramRWA] included below]

Request for providing Sewer Connection for the residents of Mahagunpuram, NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh from Builder (Mahagun Group) / Ghaziabad Municipal Corporation (Nagar Nigam Ghaziabad) / Ghaziabad Development Authority (GDA).

 

All residents residing at Mahagunpuram, NH-24, Mehrauli, Ghaziabad; MP-AOA (Regd) and AOAFG (Regd) / RWAFG (Regd) are also requested to send their requests on the above subject in the following way as it will help in speedy implementation of the same :-


---------- Forwarded message ----------


From :  Anand Kumar Sharma <anasee2162@gmail.com>

Date :  Wed, Sep 6, 2017 at 8:37 PM

Subject :  REQUEST FOR PROVIDING SEWER CONNECTION FOR MAHAGUNPURAM, NH-24, MEHRAULI, GHAZIABAD – 201002, UTTAR PRADESH FROM BUILDER (MAHAGUN GROUP) / GHAZIABAD MUNICIPAL CORPORATION (NAGAR NIGAM GHAZIABAD) / GHAZIABAD DEVELOPMENT AUTHORITY (GDA).

 

To :  Mahagun Customer Care <customercare@mahagunindia.com>, "info@mahagunindia.com" <info@mahagunindia.com>, Mahagun India <info.mahagunindia@gmail.com>, marketing@mahagunindia.com, Dhiraj Jain <mahagun@gmail.com>, scsharma@mahagunindia.com, Mayank Aggarwal <mayank.fbd@gmail.com>, anil jain <aniljain.mahagun@gmail.com>, Ajeet Chaubey <ajeetchaubey.csk@gmail.com>, Mahagun Puram <mahagunpuram.csk@gmail.com>, santosh Helpline <helplinegda@gmail.com>, vcgda ghaziabad <gdagzb@gmail.com>, bbb b <gzb.nagar.nigam@gmail.com>

Cc :  "Gen V. K. Singh" <eloksabhagzb@gmail.com>, mosvks@mea.gov.in, MOS VKS <mosvkso@mea.gov.in>, vksingh.mp@sansad.nic.in, cmup@nic.in, Yogi Adityanath <yogiadityanath72@gmail.com>, upinformation@nic.in, ncrpb-ms@nic.in, ncrpb-dr@nic.in, ncrpb-jd1@nic.in, ncrpb-aa02@nic.in, ncrcellup@gmail.com, csup@up.nic.in, shreeprakash54@hotmail.com, awas@up.nic.in, "Awas Bandhu U.P." <awasbandhu@gmail.com>, SO NAGAR VIKAS <so.nagarvikas@gmail.com>, diruplb@nic.in, fdjnlu-up@nic.in, cegjnlu-up@nic.in, zcejngz-up@nic.in, sejngz-up@nic.in, ee1cdjngz-up@nic.in, see.mjngz-up@nic.in, eecde.mjngz-up@nic.in, se18cjngz-up@nic.in, pmgjjngz-up@nic.in, gmyjngz-up@nic.in, pmy1jngz-up@nic.in, pmye.mjngz-up@nic.in, eeacujngz-up@nic.in, jdpiujngz-up@nic.in, ISHWAR CHAND JINDAL <icjindal@gmail.com>, Gaurav Dwivedi <ergauravdwivedi@gmail.com>, ashvanityagi168@gmail.com, Ashvani Tyagi <tyagia.007@gmail.com>, Saurabh Bansal <tosaurabh7@yahoo.co.in>, gargparveen1971@yahoo.co.in, RWA uttam g <uttam.singh@kanbaninfosystem.com>, Jatinder kumar <jks.gzb@gmail.com>, cyberarvind@yahoo.com, Arvind Tiwari <er.arvindtiwari@gmail.com>, "saxena111@gmail.com" <saxena111@gmail.com>, ajaykaushik74@yahoo.com, mahagunpuram aoa <mahagunpuramaoa@gmail.com>, "sheetal_tyg@yahoo.co.in" <sheetal_tyg@yahoo.co.in>, Sheetal Tyagi <sheetaltyagi1981@gmail.com>, surjeet singh <surjeet_cavs@yahoo.co.uk>, TAPAN KUMAR <smarttapan@yahoo.com>, TAPAN panigrahi <smartone.tapan@gmail.com>, gauravvanshi@yahoo.com, tanweer1008@yahoo.com, Avdhesh Kumar <avdheshks@gmail.com>, vnrsa@yahoo.com, Subhash Verma <subhashchandraverma@gmail.com>, AOA Federation Ghaziabad <aoafedgzb2015@gmail.com>, RWA Federation Gzb <rwafedgzb6@gmail.com>, Tejandra Pal Tyagi <tptyagi@gmail.com>

To

 

Vice President (Facility Management) / Director,

Mahagun Group, Mahagun India Private Limited

(Mahagun Real Estate Private Limited),

Corporate Office :  Office No. 44,  Tower – B,

4th Floor,  CORENTHUM,  Sector – 62,

NOIDA – 201309,  Uttar Pradesh.

 

Vice Chairman,

Ghaziabad Development Authority (GDA),

Vikas Path,  Near Old Bus Stand,

Ghaziabad – 201001,  Uttar Pradesh.

 

Municipal Commissioner,

Ghaziabad Nagar Nigam

(Ghaziabad Municipal Corporation),

Navyug Market,  Naya Ganj,

Ghaziabad – 201001,  Uttar Pradesh. 

 

SUBJECT :  REQUEST FOR PROVIDING SEWER CONNECTION FOR MAHAGUNPURAM, NH-24, MEHRAULI, GHAZIABAD – 201002, UTTAR PRADESH FROM BUILDER (MAHAGUN GROUP) / GHAZIABAD MUNICIPAL CORPORATION (NAGAR NIGAM GHAZIABAD) / GHAZIABAD DEVELOPMENT AUTHORITY (GDA).

 

Respected Sir,

 

1.      Kindly refer to my requests dated 15th November, 2014; 29th November, 2014; 30th December, 2014; 1st January, 2015; 3rd January, 2015; 27th April, 2015; 13th June, 2015; 21st July, 2015; Speed Post letter dated 1st September, 2015; 2nd March, 2016; 6th June, 2016; 2nd September, 2016; 10th March, 2017 and 7th June, 2017 on the above subject.  I am, once again, requesting for the same.

 

2.      Mahagun Group : Mahagun India Private Limited (Mahagun Real Estate Private Limited) started booking of Flats for their Project 'Mahagunpuram' at NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh with effect from May, 2009 onwards.

 

3.      Registry and Physical Possession of the Flats by the residents of Mahagunpuram, NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh had been done with effect from November, 2012 onwards and majority of the residents have done their Registry from Registration Office (Office of the Treasury, Ghaziabad), Tehsil, Ghaziabad, Uttar Pradesh and also taken Physical Possession of their Flats from the Builder by March, 2013 by paying all the Payments/Charges/Taxes, Stamp Duty, etc due to be paid by residents [as intimated (in writing) by the Builder :  Mahagun Group : Mahagun India Private Limited (Mahagun Real Estate Private Limited)] to all the concerned Agencies {including Mahagun Group : Mahagun India Private Limited (Mahagun Real Estate Private Limited); Central Government, State Government of Uttar Pradesh; Registration Office (Office of the Registry, Ghaziabad), Tehsil, Ghaziabad; etc}.


4.      Also, our MP-AOA [Mahagunpuram Apartment Owners Association], Mahagunpuram, NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh] had been registered with the Competent Authority in December, 2013.

 

5.      It is also hoped that Mahagun Group must have taken all the required clearances/completion certificate for the Project 'Mahagunpuram' from all the concerned Agencies (Central Government, State Government of Uttar Pradesh; Ghaziabad Development Authority; Ghaziabad Nagar Nigam; Uttar Pradesh Jal Nigam; Ghaziabad Jal Board; etc) before the Registry of the Flats / Physical Possession of the Flats to the residents of Mahgunpuram, so that Sewer Connection should have been provided to the residents of Mahagunpuram, NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh.

 

6.      Till date, no Sewer Connection has been provided to the residents of Mahagunpuram, NH-24, Ghaziabad, Uttar Pradesh even though the residents of Mahagunpuram have taken physical possession of their Flats after Registry and also by paying all the dues/stamp duty to the concerned agencies [as told to the residents by the Builder at the time of Registry/Physical Possession of the Flats at Mahagunpuram].  Due to no Sewer Connection, the problem of water logging happens regularly in Mahagunpuram.

 

7.      Shri S.S. Verma, Officer of Ghaziabad Development Authority (GDA), Vikas Path, Ghaziabad had addressed a letter dated 27th December, 2014 (copy attached) to Shri Amit Jain, Director, Mahagunpuram, NH-24, Mehrauli, Ghaziabad (with a copy of it to me for information) forwarding therewith my request on the above subject to him with directions to him to solve the problems being faced by the residents of Mahagunpuram, NH-24, Mehrauli, Ghaziabad on the above subject at his level.

 

8.      On 02 January 2015, I had also received a reply from the Office of Vice Chairman, Ghaziabad Development Authority (GDA) [helplinegda@gmail.com], as under :-

 

"Regarding this matter, please contact – 9711364673 Shri S.S. Verma, Officer, GDA".

 

9.      After receiving the above reply dated 02 January 2015, I spoke with Shri S.S. Verma, Officer, GDA on 3rd January, 2015.  He told me that he had already given directions by writing a letter to Builder on 27th December, 2014 (copy attached) for solving the problems being faced by the residents of Mahagunpuram, NH-24, Mehrauli, Ghaziabad regarding 'providing Sewer Connection' for the residents of Mahagunpuram.

 

10.    Ghaziabad, Uttar Pradesh is already an 'NCR (National Capital Region) City' since 1985 and the cities which comes under 'NCR' should have all the same common excellent facilities/infrastructure, like Excellent Roads/Widened Highways connected with Delhi and other NCR Cities; Common Transport System [Bus (DTC, UPSRTC, Autos, taxis, cabs, etc), Rail, Metro Extensions, etc) with Delhi and other NCR Cities; Safe Drinking Water for all; Sewer Connections for all; 24 Hour Electricity for all; etc. 

 

11.    On 27 August 2015, Central Government releases list of 98 Smart Cities which also includes Ghaziabad, Uttar Pradesh as a 'Smart City'.  Smart City 'Ghaziabad, Uttar Pradesh' will realize the dream of the perfect life.  The motive of each Smart City is one to accelerate economic growth and provide a better life to the citizens of the Smart City which includes sufficient water supply/water management; 24 hours power; affordable housing; pure climate; sanitation; waste management; sewer connections; better public transport (road, rail, metro, autos, taxis, cabs etc); digitization, e-governance; e-hospital (medicine, providing treatment and medical advice online, via the internet and smartphones make people aware of diseases); improved traffic; civil protection; education; health, etc.

 

12.    Ghaziabad, Uttar Pradesh is an 'NCR City' since 1985 through 'The National Capital Region Planning Board Act, 1985' published in 'The Gazette of India' on 11th February, 1985 and now it is also declared as a 'Smart City' by the Central Government on 27 August 2015, it should have all the excellent facilities as mentioned in Paras 10 and 11 above for all the citizens residing in Ghaziabad, Uttar Pradesh.

 

13.    President and Secretary of Apartment Owners Associations Federation Ghaziabad (AOAFG) [Regd] also wrote a letter dated 4th September, 2015 (copy attached) to Ghaziabad Development Authority (GDA) regarding providing Sewer Connection for the residents of Mahagunpuram. 

 

14.    Newspaper cutting of the meeting held on 2nd February, 2016 (copy attached) of President, Apartment Owners Associations Federation Ghaziabad (AOAFG) [Regd] and President / representatives, Mahagunpuram Apartment Owners Association (MP-AOA) [Regd] with Vice Chairman, Ghaziabad Development Authority (GDA) regarding Sewer Connection for the residents of Mahagunpuram is attached for information and further necessary action please.

 

15.    Also, kindly refer to meeting of 16th September, 2016 (photograph of the meeting attached) on the above subject with Vice Chairman, Ghaziabad Development Authority (GDA) in which Executive Members of Mahagunpuram Apartment Owners Association (MP-AOA) [Regd.] and Col Tejandra Pal Tyagi, President, Apartment Owners Associations Federation Ghaziabad (AOAFG) [Regd] took part for an early sanction of 'Sewer Connection' for Mahagunpuram, NH-24, Mehrauli, Ghaziabad (Uttar Pradesh). 

 

16.    On 10 March 2017, I had received a reply from Shri Mohd Mohsin Farooqui, Computer Cell, Urban Development Department, Government of Uttar Pradesh, Room No. 836, Bapu Bhawan, Uttar Pradesh Secretariat, Lucknow – 226001 (cc.urbandev@gmail.com) addressed to me and to the Secretary and Officer on Special Duty, Urban Development Department, Government of Uttar Pradesh, Room No. 834, Bapu Bhawan, Vidhan Sabha Marg, Lucknow – 226001 (awasbandhu@gmail.com), as under :-

 

"I am directed to inform you that the matter is related with Housing and Urban Planning Department. The same has been forwarded to them for necessary action".


17.    Kindly refer to letter dated 02 May 2017 (copy attached) of Shri RP Singh, General Manager (T) / Project Director, National Highways Authority of India (NHAI) [Ministry of Road Transport & Highways], Project Implementation Unit, Ghaziabad, House No. 518, Niti Khand – 1, Indirapuram, Ghaziabad – 201014 (Uttar Pradesh) addressed to the Vice Chairman, Ghaziabad Development Authority (GDA), Ghaziabad (Uttar Pradesh) regarding 'permission for the access to the drainage system of proposed NH–24'.

 

18.    Kindly refer to letter dated 20 June 2017 (copy attached) of GDA addressed to the concerned authorities with copies of it to MP-AOA / Builder / other concerned authorities regarding Sewer Connection for Mahagunpuram and also intimating convening of meeting on 24 June 2017 at 1230 hours with Vice Chairman, GDA on this subject.

 

19.    In the meeting held on 24 June 2017 at GDA Conference Room between representatives/officers of MP-AOA, Builder and GDA, the following actions on this subject were decided to be taken at the earliest, as under :-

 

"आज दिनांक 24 जून 2017 को जीडीए के सभागार में माननीय उपाध्यक्ष द्वारा महागुन पुरम में ड्रैनेज/निकासी की समस्या के हल के लिए बिल्डर महागुन रियल एस्टेट प्राइवेट लिमिटेड ,महागुन पुरम एसोसिएशन जीडीए के उच्च अधिकारीगण की मीटिंग बुलाई थी |

 

जिसमें जीडीए की तरफ से श्री आर के जायसवाल अधीक्षण अभियंता , श्री कप्तान सिंह अधिशासी अभियंता प्रभारी - प्रवर्तन विभाग।

 

महागुन की तरफ से श्री एस सी शर्मा वाइस प्रेसिडेंट कमर्शियल, श्री प्रदीप  कुमार शर्मा आकाश जैन।

 

महागुन पुरम एसोसिएशन की तरफ से श्री ईश्वरचंद जिंदल अध्यक्ष , श्री गौरव द्विवेदी महामंत्री, श्री शीतल त्यागी पूर्व अध्यक्ष, श्री ओम पाल सिंह ,श्री उत्तम राणा श्री जेपी चंद्रा उपस्थित थे।

 

लगभग एक घंटा चली इस मीटिंग का परिणाम निम्नलिखित रहा

 

जीडीए ने स्पष्ट रुप से बताया, बिल्डर द्वारा दिए गए शपथ पत्र के आधार पर महागुन पुरम प्रोजेक्ट की स्वीकृति नो वाटर डिस्चार्ज शर्त के ऊपर दी है। इसको बिल्डर के प्रतिनिधियों ने स्वीकार किया। 

 

बिल्डर ने बताया 10 करोड़ रुपया ईडीसी के रूप में जमा किया है और यह जिम्मेदारी जीडीए की है कि वह ड्रेनेज की व्यवस्था करा कर दें |

 

जीडीए ने कहा कि वह ड्रेनेज बनाने के लिए तैयार हैं, परंतु प्रोजेक्ट अप्रूवल के समय लगाई गई शर्तों के अनुसार जो भी खर्चा होगा वह उसमें से ईडीसी का पैसा काट कर बाकी बिल्डर को देना होगा। आज के दिन ड्रेनेज बनाने के लिए भूमि अधिग्रहण अन्य खर्चों में लगभग 550 करोड़ रुपए की अनुमानित लागत है, जिसमे ईडीसी का पैसा काट कर बाकी का बिल्डर को देने होगे।

 

जी डी ने बताया, समस्या के हल के लिए एक सलाहकार की भी नियुक्ति की गई है। साथ ही एनएचएआई के अधिकारियों से भी संपर्क किया गया है ताकि कोई व्यवस्था बनने वाले एनएच-24 में हो जाये।

 

बिल्डर ने बताया, एसटीपी से निकले पानी  के डिस्पोजल पर अब तक  लगभग डेढ़ करोड़ रुपया  खर्च हो चुका है। उन्होंने यह भी स्वीकार किया जब तक ड्रेनेज की व्यवस्था नहीं हो जाती है, तब तक जो भी खर्चा उसके डिस्पोजल पर आएगा वह बिल्डर वहन करेगा।

 

 जीडीए ने बिल्डर को यह निर्देश दिया , अगले 15 दिनों के अंदर बिल्डर  ड्रेनेज की समस्या के समाधान हेतु कोई समग्र प्रस्ताव प्रस्तुत करें। अगली मीटिंग 15 दिन बाद होगी।

 

साथ ही, कंप्लीशन सर्टिफिकेट पर बताया गया कि वर्तमान ड्रेनेज समस्या के चलते बिना आरडब्ल्यूए को  विश्वास में लिए  सर्टिफिकेट जारी किए जाने की कोई संभावना नहीं है।"

 

20.    Photograph and News Article relating to the meeting held on 24 June 2017 with Vice Chairman, GDA for Sewer Connection for Mahagunpuram, NH-24, Ghaziabad are attached.

 

21.    Kindly refer to letter dated 26 June 2017 (copy attached) of President, MP-AOA addressed to Hon'ble Chief Minister of Uttar Pradesh regarding Sewer Connection for Mahagunpuram.

 

22.    Kindly refer to letter dated 28 June 2017 (copy attached) of President, MP-AOA addressed to Vice Chairman, GDA regarding Sewer Connection for Mahagunpuram.

 

23.    In view of the above, it is requested that necessary instructions may please be issued to the concerned officers/officials so that the residents of Mahagunpuram, NH-24, Ghaziabad should be provided 'Sewer Connection' at the earliest by the Builder (Mahagun Group) / Ghaziabad Nagar Nigam (Ghaziabad Municipal Corporation) / Ghaziabad Development Authority (GDA) as already considerable delay has been occurred in this regard.  The problem of water logging happening regularly in Mahagunpuram will also be sorted out by the Sewer Connection in Mahagunpuram.  We all will be highly grateful to you for that.

 

24.    Kindly acknowledge and confirm.

 

Regards.

 

Anand Kumar Sharma

Date :  6th September, 2017.

Address : Flat No. 1106, Riddhi Block, Mahagunpuram, NH-24, Mehrauli, Ghaziabad – 201002, Uttar Pradesh.

                                           

Attachments :  As stated above.

 

Copy for information and further necessary action please (for requests/directions, etc to the concerned authorities) to :-

 

1.      Hon'ble Union Minister of State for External Affairs / Overseas Indian Affairs and Hon'ble Member of Parliament (Lok Sabha : Ghaziabad Constituency), 2/27, Raj Nagar, Ghaziabad – 201002, Uttar Pradesh.  Kindly acknowledge and confirm.

 

2.      Hon'ble Chief Minister of Uttar Pradesh, Lucknow – 226001, Uttar Pradesh.  Kindly acknowledge and confirm.

 

3.      Member Secretary, National Capital Region Planning Board (Ministry of Urban Development), Core–IV B, First Floor, India Habitat Centre, Lodhi Road, New Delhi – 110003.  Kindly acknowledge and confirm.

 

4.      Chief Secretary, Government of Uttar Pradesh, Lucknow – 226001, Uttar Pradesh.  Kindly acknowledge and confirm.

 

5.      Principal Secretary / Secretary – Housing & Urban Planning (Chairman – Ghaziabad Development Authority), Government of Uttar Pradesh, Lucknow – 226001, Uttar Pradesh.  Kindly acknowledge and confirm.

 

6.      Commissioner, NCR  Planning & Monitoring Cell (UP), Town & Country Planning Department, Navyug Market, Second Floor, Nagar Nigam Bhawan (Commercial Building), Ghaziabad, Uttar Pradesh – 201001.  Kindly acknowledge and confirm.

 

7.      Managing Director & Officers of Uttar Pradesh Jal Nigam (UPJN), Head Office : 6, Rana Pratap Marg, Lucknow – 226001, Uttar Pradesh; Chief Engineer (Ghaziabad) & Officers of UPJN, Ghaziabad and Chief Engineer (Ghaziabad Zone) & Officers of Ghaziabad Jal Board, Uttar Pradesh Jal Nigam, Sector – 1, Raj Nagar, Ghaziabad.  Kindly acknowledge and confirm.

 

8.      President / General Secretary / Executive Members of Mahagunpuram Apartment Owners Association (MP-AOA) [Regd.] of Mahagunpuram, NH-24, Mehrauli, Ghaziabad, Uttar Pradesh – 201002.  Many thanks for promptly pursuing the matter with the concerned authorities.  You are also kindly requested to write again on the similar lines as it will help in speedy implementation of the same.  Kindly acknowledge and confirm.

 

9.      President, Apartment Owners Associations Federation Ghaziabad (AOAFG) [Regd], Registered Head Office : 133 – B, Model Town East, Ghaziabad – 201009, Uttar Pradesh.  Many thanks for promptly pursuing the matter alongwith our MP-AOA with the concerned authorities.  You are also kindly requested to write again on the similar lines as it will help in speedy implementation of the same.  Kindly acknowledge and confirm.

 