This weekend, I had a chance to visit mahagunpuram site ater long time. I visited one of the flats in Rddhi (1300 SQ FT) and another in Vinayak (900 SQ FT). I had below observation, which I did not like... Please let me know, if you had similar observation/opinion.

1. None of the flat's rooms are exactly rectangle/Square in shape. At least one side of the walls is projected. When I checked with my agent, he told that it is a design. But then I observed in all the rooms incuding hall !

2. The lavatory (latrine) sheet is being fitted exactly in the mid of the bathroom . The bath shower will be at the far corner. This means, after you have taken a bath (pure), you have to pass along the lavatory sheet (impure) to exit. Not a very comfortable situation, specially for religious people!

3. The beam of the architecture is eating into the Cabinet/Almiraah space. This looks eagly due to unwanted projection of the beam, and also almiraah space is crunched (You can not make even a 6/3 standard almiraah through wood work.)

4. The vitrified tiles in the rooms are of cheaper quality (Small in size). I was expecting them to at least fit  larger size tiles in the Drawing Room (Hall), which looks decent.

5. The kitchen drainage pipe of the overhead flat is passing through kitchen. If you just peep at the kitchen ceiling, you can see that. Ideally drainage pipes are fitted along the outer walls. My agent told me, that this would be covered by false ceiling. But it seems a poor design.

6. The similar observation with the drainage pipe in Bathrooms. think of a situation, if you overhead flat's bathroom has developed a leakage. In order to repair that, plumber will break your cieling ?



I had reached at the site at the end of the day, so could observe this only in dim light, but really not happy with this all.

Just a question? Do Mahagun's other projects have the same design?

Please pour your opinion?

26 comments:

Gyani said...

No opinion ... ??????

NARENDRA said...

These observations are correct. All the beams/pillars are projected in all the rooms including kitchen which are not looking good and eating space. window of the Attached bathroom is very small that to with fix fitted glass. At present there is no place for ex fan or ventilation.They are fitting all the sewage pipes on the top of bathroom/kitchen covered by false ceiling. it will create lot of problem in case of leakage. I do not have any idea about other projects of Mahagun.

Manoj Kumar Dhankhar said...

yes, i observed the false ceiling in the flat and definitely will have problem. Can we all do something because individually cannot win with builder to change the layout(will say its part of design). brochure also does not contain related to this.

Frankly speaking, i have no idea what to do?

Vinay Saini said...

Hi Guys,

Let meet at the earliest probably this Sunday 2ndJan2011 at Mahagunpuram. I think this is a serious issue and need to be dealt/discussed at the earliest before its too late. Lets spare sometime and meet. Can any of us take the initiative in coordinating the meet. As we have already shared the contact details. Lets decide the time and confirm the same.

Gyani said...

Friends.. Sorry for delay in response.. Actually busy in shifting..

I am again planning to go this sunday, 9th Jan.

I would request that for whomsoever, it is possible; please come to the site, and we can talk with the builder on the spot.

Please let me know..?

Anonymous said...

Hi Gyan,

Let me know the date and timing. Also provide me with you contact details. You can reach me at 9654198351.

Thanks
Vinay

Pradeep said...

Hi Friends,
Good observation and initiative. Timely escalation and resoution will save us from probems in future. We all need to discuss with builder. I would like to join

Thanx
Pradeep
9971999748

Pradeep said...

Hi Friends,
Good observation and initiative. Timely escalation and resoution will save us from probems in future. We all need to discuss with builder. I would like to join

Thanx
Pradeep
9971999748

Manoj Kumar Dhankhar said...

hi guys,
I was on site yesterday(9jan11) along with Mr. Vinay, Mr. Akhilesh and Mr. Shyamal(new member) and had discussion with Mahagun person (site office) about the issues.
Here is the summary:
About point no 5: Drainage pipe will not be there in the kitchen as mahagun changed the plan and now the kitchen drainage pipe will not go through your flat. Good News!!!
About Point no 6: after observation, I personal didn’t find any issue with this. In case of any leakage of your overhead’s flat , you can easily fix this by removing false ceiling, however in normally ceiling you have to break overhead’s flat’s bathroom to repair pipes.
However there is no plan for other issues and will stay as per design.

At the end, he gave a number of a person(I forgot the name) to whom we can have communication regarding the issues during week days. Mr Akhilesh is having that number along with you. I would like Mr. Akhilesh to publish that number on the blog.

NARENDRA said...

HI FRIENDS
THANKS TO PURSUE THE MATTER. IS THERE ANY DISCUSSION ON POINT NO 4 & SPACE FOR EX FAN IN ATTACHED BATHROOM.

Manoj Kumar Dhankhar said...

Sorry Mr. Narendra,

we had discussion only for point 2,3,5,6 not for point 4 and ex fan...

Pradeep said...

Hi friends,

What abuout Point 2 and 3. Is there any solution.

Pradeep

Manoj Kumar Dhankhar said...

soory.. for delay...was out of touch.

No solution for point 2 and 3. will be as it is!!!

Unknown said...

I've paid some of the installments for the open parking... But don't want to pay any more after reading this post..What should i do??

Pradeep said...

Hi friends ,

shall we plan to meet at site and review the current status.

saurabh said...

hi....friends,

i've just booked a flat in mahagunpuram at ground floor.
plz do let me know that i have done it right or wrong..



regards
saurabh bansal
09717138222

akhil said...

any idea when mahagun puram will increase price

Vips2810 said...

Guys....any update on construction status..????

saurabh said...

construction is on its swing..
almost all towers are standing..
plaster electric and water fitting is just started in some of the towers..
regards
Saurabh Bansal
09717138222

ravi said...

Hi All,

Pls do let me know whenever group is planning to visit the site.

Rgds
Ravi Arora
9999 380037

Umesh said...

If someone visit the site, plz post the recent pics....

Umesh said...

.gud news as well..Goverment also planning to open a new IIIT at NH 24.. Lets see how long it will take.

ash said...

Hi Umesh,

Indeed a good news...
from where did u get this news.

Rohit said...

hello all,
i have uploaded some photos in the picasa web albums and also shared the the same link in facebook under mahagunpuram group.......

Vipul said...

Hi Rohit.

Thanks for the update....but some of us do not have access to facebook...

It'll be great of you could share the link here also...

Regards,
Vipul

Anonymous said...

hi i m very new in delhi and just wanted to book a flat. in phase 1 they are giving ready to move in flats with possession date dec 2011. is it a good idea to go with mahagunpuram. pls suggest