Hi Nikhil,
During the greater noida issue once when it was becaming difficult to continue Mywoods project, the alternate options were given to the customers...e.g. giving option in other Mahagun projects or refund of money etc.
lets hope for the best...we really need to close watch on it.
with regards, Dheeraj
From: Nikhil Gupta <nikhil.gupta07@yahoo.com>
To: "dheerajbh@yahoo.com" <dheerajbh@yahoo.com>
Cc: MahagunpuramRWA@yahoogroups.com
Sent: Saturday, February 9, 2013 7:38 AM
Subject: Re: [Mahagunpuram] update on Mahagunpuram-Phase-2
To: "dheerajbh@yahoo.com" <dheerajbh@yahoo.com>
Cc: MahagunpuramRWA@yahoogroups.com
Sent: Saturday, February 9, 2013 7:38 AM
Subject: Re: [Mahagunpuram] update on Mahagunpuram-Phase-2
Hey Dheeraj
It would be great if you can brief me about what had happen in Mywoods project, a I am unaware of the this past issue by Mahagun
It would help me understanding the further betterRegards
Nikhil Gupta
NARMADA TOWER
Today i visited Mahagun office in Noida to pay service tax demand. I enquired about the progress on Phase-2 ( although i had visited site and don't see any progress). Mahagun's executive Mamta told that...they have not received various approval from authorities and she was very hesitant to provide more information. She said by the end of March, they will decide upon action plan...it may include shifting of Units i.e. offering something else to buyers...the way they have done in Mywoodsregards, Dheeraj
__._,_.___
No comments:
Post a Comment