HI , THANKS FOR THE UPDATES. IT SEEMS THEY WILL TAKE MORE THAN ONE YEAR TO GIVE THE POSSESSION WITH THIS PACE OF WORK...... IT WAS JUST THE MARKETING STUNT TO " POSSESSION IN 6 MONTH GURANTEED" . THIS BUILDER MADE US FOOL ... WE ARE ALL GIVING THE EMI AND RENT.
IT IS DISASTER.....
WHITE WASH HAS JUST STATTED , NO BATH FITTING , NO ELECTRICITY FITTING, NO WOODEN WORK LIKE DOORS AMD WINDODS AND NO PLASTER TILL.
HOW WE CAN ASUME THAT THEY WILL GIVE POSSION IN JUNE IT LOOKS NEXT JAN OR FEB IT MEANS 12-15 MONTH MORE.....
Is the builder within its right to hand over one building if it gets completed say in June and rest are completed later. While I don't know the legal aspects but it would be unfair as the place would be unlivable with construction going all around.
Also, can you confirm if they can give possession before the club house, swimming pool and shopping area is completed
i have posted a request that we all meet and disucss common problems this weekend , if u really want then call me and and meet this weekend- 9650163152
10 comments:
no progrss will take another 6 months to get possession at least..
HI , THANKS FOR THE UPDATES. IT SEEMS THEY WILL TAKE MORE THAN ONE YEAR TO GIVE THE POSSESSION WITH THIS PACE OF WORK...... IT WAS JUST THE MARKETING STUNT TO " POSSESSION IN 6 MONTH GURANTEED"
.
THIS BUILDER MADE US FOOL ... WE ARE ALL GIVING THE EMI AND RENT.
IT IS DISASTER.....
WHITE WASH HAS JUST STATTED , NO BATH FITTING , NO ELECTRICITY FITTING, NO WOODEN WORK LIKE DOORS AMD WINDODS AND NO PLASTER TILL.
HOW WE CAN ASUME THAT THEY WILL GIVE POSSION IN JUNE IT LOOKS NEXT JAN OR FEB IT MEANS 12-15 MONTH MORE.....
Internal progress of the building is need to be analyzed. The external work should take somewhat ~7 months.
Seems like only one building is on the way for June delivery.
Amit,
Is the builder within its right to hand over one building if it gets completed say in June and rest are completed later. While I don't know the legal aspects but it would be unfair as the place would be unlivable with construction going all around.
Also, can you confirm if they can give possession before the club house, swimming pool and shopping area is completed
Ashish
@Ashish,
Let me give you in written [1/0 = infinite percent sure] that they are not going to handover club etc before 2 yrs, after you start living :D
Simple, Builder do not have to pay any penalty for club-not-ok-on-time case.
Lets pray that we get possession soon.. but as you said, even though possession is given, it will not be livable.
Of course we have legal option against this, because 'Possession' means 'Completely livable'. But we need to be united, and somebody to lead.
Very well said Gyani...
Its logical to understand the reason for a hasty delivery of individuals flats.
Ashish, its physiological to understand your question; as we share the similar agony of late delivery of our homes.
You should review the progress personally, to create a general understanding of situation....
i have posted a request that we all meet and disucss common problems this weekend , if u really want then call me and and meet this weekend- 9650163152
Vikas, I really appreciate your thought and step.
I would have loved to come along, but I am quite occupied in Weekend due to office work :(
what is ur name Admin? can I have ur contact number? or can u call me plz?
Thanks for d updates to all
can anyone tell me d most likely date of ganga tower possession
for other towers, wheather anyone gets d late penalty cheques from mahagun
image 5 is of ganga tower