| Hi All Phase 2 members
I too had a conversation with Marketing head: Mr Sachin, following were the points of discussion,
- the issue informed was additional FAR approval which is pending with GDA without which one can't go for construction.
- I asked for the copy of all for Mahagunpuram Ph2 docs being approved till now/submitted pertaining to GDA, which was considered by him and said after pondering that he may provide it to us, provided we go to him with prior appointment with him.
- Time told to me was, with in a week they should get some conclusion from GDA.
Things to ponder now
- Why Mahagunuram always forward the Marketing Head as contact person for all grieviences which in fact has no role in post sales talks. Well i know Mahagun is not a listed company but a reputed (as what people says) always has a legal body (with some lawyers), dedicated customer care/customer grievence with high designated persons who handles with people queries like this with supported docs. I am saying this from my past experiences with Unitech, DLF & Paravsnath. Though they are big companies but this is some thing being mandated by Corp Governance.
- Why company raised FAR which is nothing but increasing no of flats & made fool of early customers? why it changed plan later? well i am not sure about the legal side of it but something is fishy.
- Well, as he is ready to show the docs, so i think we must not miss the opportunity to get the copies from them by arranging a collective meeting with them in their Noida office which may be in later stage can be matched with from GDA ones if some mishap happens.
So lets organize a meeting asap. Regards Nikhil Gupta +91-8882355118 --- On Sat, 2/3/13, Rahul Tiwari <rahul.tiwari123@gmail.com> wrote: From: Rahul Tiwari <rahul.tiwari123@gmail.com> Subject: Re: [Mahagunpuram] All Phase-2 Members Please Increase the Count for Saturday Meeting at Mahagun To: MahagunpuramRWA@yahoogroups.com Date: Saturday, 2 March, 2013, 4:59 PM
Guys ,
As per last conversation with Mahagun representative Mr. Sachin , it was clear that Mahagun applied for additional FAR after project was approved by Banks . Now Mahagun will not start construction unless new FAR is approved by GDA.
So bottom line is : how to get Mahagun working on old FAR or force them to buy new FAR soon ? On Sat, Mar 2, 2013 at 4:16 PM, Saumyajit Ray <ray.saumyajit@gmail.com> wrote: Dear All Phase II members,
If Mahagun officials cannot furnish a firm date for beginning reconstruction, it is really a matter of serious concern. They will never give a clear picture to home-buyers. RTI is one way of getting to know the status of approval. But how come banks, both private and nationalized, are extending loans to customers in a project which is not approved by the state government? Anyway, lets meet them without delay to sort out things. A big group of Phase-II buyers is necessary to meet them, not just 4-5 people. I regret not having gone the last time.
Regards,
Dr. Saumyajit Ray (Asst. Professor, Jawaharlal Nehru University, New Delhi) #971, Kaveri 9868337072 On Sat, Mar 2, 2013 at 3:34 PM, kbk2626 <kbk2626@yahoo.com> wrote: Dear all, being a new member, would like to request all to arrange meeting in holidays/sunday so that we can approach maximum numbers. like myself working in a pvt firm where its all most not possible to visit outside in working hours and even I dont get time to access mail due to really tight schedule, like wise may be other reason for otherones. but we should find one more option to aware/share about any important information timely with others so that at least we can approach/call them for at least for a very important meeting. thanks KHATRI KAVERI, ;PHASE-2 > Let's arrange formal meeting with them, including the top managers from Mahagun pyramid and the same is required to be informed to media. > > I am currently in the process of drafting RTI TO GDA to furnish approval to Mahagunpuram. I would request shall try working in this direction else I apprehend Mahagun is taking us in some other way. > > Regards > Nikhil Gupta > +91-8882355118 > > On 01-Mar-2013, at 10:29 AM, "Shailandra" wrote: > > > > > > > Dear Phase 2 members > > > > Yesterday I discussed with Mahagun representative regarding re-launching of Phase-2 and on construction updates as it was expected to resume by end of Feb, 2013. > > But unfortunately Mahagun Rep was not in the position to explain the current status and told that there is no any firm date of re-launching and can not confirm when construction will resume again. I think we should meet again at Mahagun office or at site to clarify the issue and to decide the further actions. > > > > It is now very serious concern for all of Phase 2 members. > > > > Regards > > > > --- In MahagunpuramRWA@yahoogroups.com, "Ravinder" wrote: > > > > > > Hi > > > > > > Pls count me in. > > > > > > Ravinder > > > 566 kaveri > > > 9958799964 > > > Ravinder > > > > > > -----Original Message----- > > > From: Ankit Mittal > > > Sender: MahagunpuramRWA@yahoogroups.com > > > Date: Mon, 18 Feb 2013 05:54:09 > > > To: MahagunpuramRWA@...@ yahoogroups.com> > > > Reply-To: MahagunpuramRWA@yahoogroups.com > > > Subject: Re: [Mahagunpuram] All Phase-2 Members Please Increase the Count for Saturday Meeting at Mahagun > > > > > > Hi All, > > > > > > Thanks to everyone for putting their efforts on phase II construction issue. Is there any way to get a list of all buyers of Phase II so that we can contact them and raise our voice with more power to make some pressure on builder. Right now everybody is not on this forum. However builder has confirmed that construction and booking will be open from March first week but we should not fully rely on them. > > > > > > Please keep updated. > > > > > > Thanks > > > Ankit > > > 9811284316 > > > > > > > >
|